Metro Express to start commercial operations in Curepipe in two months

Published

on

Metro Express to start commercial operations in Curepipe in two months

The Metro Express will start commercial operations at the Curepipe Central Metro Station (CCMS) around the end of September or early October 2022 as significant progress has been made in the implementation of the project so far.

The first Light Rail Vehicle will be effecting trial tests up to the CCMS as from 20 July 2022, and this exercise will span over some two months.

Seven stations are currently under construction and will be ready on time so that the Metro Express can be fully operational from Curepipe to Port Louis. An Urban Terminal will also be constructed in Curepipe.

Metro Express to start commercial operations in Curepipe in two months
Photo: GIS Mauritius

To date, some eight million commuters have reportedly used the Metro Express.

A feasibility study to extend the Metro Express from CCMS to La Vigie has reportedly been carried out – the aim is to extend the Metro Express Project around the country.

Original article at GIS Mauritius

Bookmark (0)
ClosePlease login

No account yet? Register

Spread the News
The information and opinions expressed in our published works are those of authors/sources believed to be reliable. NewsMoris makes no representations as to accuracy, completeness, suitability, or validity of any information expressed.
Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

The information and opinions expressed in our published works are those of authors/sources believed to be reliable. NewsMoris makes no representations as to accuracy, completeness, suitability, or validity of any information expressed.